30,000 sq. ft office fit out on Georges Quay for Twitter Dublin HQ.

Haughton and Young were awarded the mechanical services contract for the 30,000 sq. ft office fit out on Georges Quay for Twitter Dublin HQ. This involved a complete strip out of the 2nd floor and 50% of the 3rd floor. The project was carried out in a live environment throughout the high end office fit out and updating of existing mechanical systems. All work was carried out with noise restrictions in place to avoid disruption to the client. This approach allowed us to overcome the landlord’s initial concerns of the works and our experience with the client allowed the project to run smoothly and to culminate in a snag free handover

twitteroffice2Scope of Works

Mechanical Services Installation

  • The extension and modification of the condensate installation to relocated and new FCU’s and AC units
  • New Hepvo traps to all FCU’s & AC units
  • Condensate full test to every FCU at commencement of project
  • New drip trays for the comm’s room AC installation
  • New soils and waste connections to all new locations
  • Testing & Commissioning
  • H&S and O&M Manuals

 

twitterpipes

 

Project Team

Architect Michael Collins Associates
M/E Consultant Metic Consulting Engineers
Main Contractor Flynn Management & Contractors Ltd.
Project Duration September 2014 – October 2014